Use case 1Condition-based maintenance into the next planned stop
A critical asset showing early wear is usually caught by monitoring, then lost in the hand-offs between maintenance, stores and production planning. Closing that loop means fewer unplanned stops without adding stops of its own.
“Press line 3 is vibrating above alarm: can we fix it in this weekend’s changeover, or do we need to stop the line?”Asked by a maintenance planner
- Context
- CMMS: Press line 3 main drive, criticality A, main bearing last replaced 14 months ago
- Condition monitoring: vibration velocity at 7.1 mm/s against a 7.0 mm/s alarm, rising steadily for 9 days
- MES / APS: next planned stop is Saturday’s changeover in 4 days, a 6-hour window
- ERP stores: 2 matching bearings on hand; a qualified fitter is rostered on Saturday
- Rule
- If a criticality A asset is above vibration alarm, a planned stop falls within 7 days, and the part and a qualified technician are available, schedule the replacement in that stop; otherwise escalate to the maintenance manager.
- Decision
- Replace in the next planned stop Severity: Medium
- Agents
- Condition agent Reads the vibration trend and fault frequencies and explains that the signature points to bearing outer-race wear rather than misalignment.
- Planning agent Finds the Saturday window in the production plan and checks the job fits inside it with the fitter’s other tasks.
- Parts agent Reserves one bearing and the seal kit in stores so the job is kitted before the stop starts.
- Policy
- Planners may schedule work orders inside an existing planned stop without further approval. Anything that extends a stop or changes the production schedule needs the production manager. The job carries a lockout/tagout permit, issued on site by an authorised person.
- Action
- Work order created in the CMMS and released automatically into Saturday’s stop, bearing kit reserved in ERP, production schedule unchanged.
- Data
- Asset register and maintenance history (CMMS)Condition-monitoring and historian dataProduction plan and planned stops (MES / APS)Spares stock and reservations (ERP)Technician skills and rosters
Use case 2Process drift on a special characteristic
When a critical dimension starts to drift, the cost is decided by how fast the affected lots are found and stopped before they ship. Fast containment means fewer escapes, fewer customer complaints and less scrap.
“CNC cell 5 is drifting on the bore diameter: which lots are affected, and is anything on its way to the customer?”Asked by a quality engineer
- Context
- QMS control plan: housing H-220 bore diameter is a special characteristic, 42.000 mm plus or minus 0.015 mm
- SPC: the last 8 subgroups sit above the centre line; Cpk has fallen from 1.6 to 1.1
- MES genealogy: lots L-0912 and L-0913 produced in that window, 1,800 parts, 600 already in finished goods
- WMS: none shipped yet; next dispatch to Northfold Axle Works is in 2 days
- Rule
- If a special characteristic shows a run of 8 or more points on one side of the centre line, or Cpk falls below 1.33, hold every lot made since the last good check and raise a nonconformance for disposition.
- Decision
- Hold lots and refer for disposition Severity: High
- Agents
- SPC agent Confirms the run rule and capability breach on the cell and shows when the drift started.
- Traceability agent Walks the lot genealogy from the cell to finished goods and the pending dispatch, so nothing affected is missed.
- Root-cause agent Links the drift to the tool-change counter and to similar past events on the cell, and proposes a likely cause for the engineer to confirm.
- Policy
- Agents may place a quality hold, because it is protective and reversible. Only a quality engineer may disposition the lots (rework, scrap or use as is). Use as is on a special characteristic needs the customer’s written deviation approval, as the customer-specific requirements under IATF 16949 expect.
- Action
- Quality hold placed on both lots in MES and WMS, the dispatch line held, and a nonconformance raised in the QMS and referred to the quality engineer for disposition.
- Data
- Control plans and special characteristics (QMS)SPC measurements by cell and toolLot genealogy and work orders (MES)Finished goods and dispatches (WMS)Customer requirements and deviation history
“Can we promise Brindlemoor Fixings 2,000 brackets by Friday without hurting other orders or losing money on it?”Asked by a customer service manager
- Context
- ERP order entry: request for 2,000 brackets due in 5 days, order value £24,000 at standard price
- APS: line 2 can make 1,200 in regular shifts this week; the other 800 need one Saturday overtime shift
- Costing: contribution at standard is £5,800; overtime and expedited steel freight add £2,900, leaving £2,900
- Commercial policy: expedited orders need a contribution floor of £3,600; no other order slips if the overtime runs
- Rule
- Confirm automatically if the order fits regular capacity and contribution stays at or above the floor; if it needs overtime or falls below the floor, hold it for approval.
- Decision
- Accept only with approval Severity: Medium
- Agents
- Capacity agent Tests the order against the finite schedule and shows that regular shifts cover 1,200 and that no existing order moves.
- Margin agent Builds up the cost of overtime and expedited freight and shows the contribution falling below the floor.
- Customer agent Reads the account history and terms and proposes an alternative: 1,200 by Friday and 800 the following week at standard cost.
- Policy
- Customer service may confirm orders within standard lead time and margin. Overtime needs the plant manager, within working-time limits. Contribution below the floor needs the commercial manager.
- Action
- Order entered in ERP as pending approval with two options (full quantity with overtime, or split delivery); no delivery promise sent to the customer until it is approved.
- Data
- Sales orders and customer terms (ERP)Finite capacity and schedules (APS / MES)Standard costs and freight ratesMaterial availabilityCommercial approval limits